Montage
Central Communications

DHS LogoCentral Communications, Inc.

d

wreck

NEW Facilities of
Central Communications

 

 

 

In 2007, CCI purchased the Pennsboro VFD training center, and began re-modeling it for use as a new 911 center. The new building will provide much needed space for our operations.

The original center had use of around 880 square feet of floor space, including the restroom, equipment room, dispatch room, foyer, one office and a small area in the waiting room of the State Police office. Typically there are 7 people working in these areas during the day shift. The parking lot is approximately 75 feet away, so any equipment and supplies have to be carried to the building.

The new building in Pennsboro will provide us with around 7000 square feet, plus an adjacent parking lot, and close proximity to stores and eating establishments. We moved into and began accepting calls in our new center on November 18th, 2008 with minimal issues - almost exactly one year to the day from starting the building modifications.

One thing we will definitely miss is the close relationship that we had with the officers and employees of the WVSP West Union Detachment. However, we won't totally sever the physical ties, as most of the equipment will remain in the current center, and it will become the backup PSAP after the move.

 

New 1
   
This is the view of the building from Lamberton Road, prior to any modifications.
   
New 2
New 3

This is an inside view towards the rear, prior to any modifications.

This is the view towards the front of the building, also prior to any modifications.

   
New 3
New 4

The demolition starts..

Installation of a sewer line to the new restrooms and kitchen.

New 5
New 6

The new walls starting to go up.

The water distribution system and the hot water tank which was moved from the rear of the building.

   
New 7
New 8
The Dispatch Room showing the raised flooring in white.

The coffered ceiling in the Dispatch Room.
Hard to visualize in this "bare" state.

   
New 8
New 9
A partial shot of the Equipment Room while still empty.
This is a shot from above the Dispatch Room, with the kitchen to the right.
   
New 10
New 146
Looking from the front door in to the Conference/Training Room.
Boring the caissons for the 160' tower.
   
New 153
New 166
Clearing the 36" auger.
Looking through the Equipment Room to the outside door.
   
New 161
New 162
The Conference/Training Room is still being used for staging.
The nearly complete Dispatch Room. The black squares are acoustic panels, which reduce echoes in the room.
   
New 157
New 160
A detail of the coffered ceiling.
The kitchen is also nearly complete.
   
New 185
New 188
Vendors installing equipment at the Dispatch positions.
Part of the LAN network wiring going to the Dispatch positions.
   
New 192
New 177
The LAN patch panel, partially interfaced.
Miller Communications installing a temporary tower for the radio links.
   
Tower 1
Tower 2
Miller Communications and Morlan Construction in the early stages of erecting the 160' tower.
Tim Miller and Richard (last name unknown) of Miller Communications installing cross braces.
   
Tower 3
Tower 4
Tower sections pre-assembled and waiting for a crane to install them.
The pre-assembled sections again. There are 2 more sections to assemble.
   
Last updated 01/06/09 Page 2